Construction of PON 2024 site in Aceh reaches 75 percent, DPR demands to speed up progress


Aceh – Commission Meanwhile, there are less than two months left until the opening of the Aceh – North Sumatra PON.

Read also:

Jokowi signs new Perpres, Compensation Procedure for Land Affected by IKN Development

According to the DPRK commission, the number of votes in the main venue, which was the inaugural venue at the Harapan Bangsa Stadium in Banda Aceh, was already 78.68 percent.

“In fact, there are several pools, for example the pools, there is equipment that has to be sent from abroad, so the tender that was made last May was for 4 sites, we hope it can be expedited,” said the member. . X Commission of the House of Representatives, Illiza Saaduddin Jamal together after visiting the Harapan Bangsa Stadium, Friday, July 12, 2024.

Read also:

Jokowi signs presidential decree to accelerate development of IKN, the 190-year guaranteed investor-owned HGU

According to him, it is necessary to ensure that the deadline for the completion of construction and the opening ceremony is not too short and to ensure that all fields are tested by participants before the match.

According to the information provided, the construction of the PON site in Aceh will be completed in stages and will be ready for use by mid-August 2024.

Read also:

PDIP’s Jarot says IKN development is forced, Grace Nathalie reminds ‘beware of landslides’

“It was presented earlier, all the works have reached more than 75 percent, we are optimistic that it will be finished by the end of August. “But there are also (places) that are really looking forward to its completion,” he said.

The progress of PON field construction in Aceh, especially in Banda Aceh City, Harapan Bangsa Stadium 78.68%, H Dhimurthala Stadium 75.93%, PABSI Building 83.68%, Fencing Hall 89%, Jasdam Tennis Court 66.95% and Police Regional Tennis is 88 percent. . .

So, the construction progress of the tennis court at the SB complex is 71.87%, Gore Koni Aceh is 67.10%, tennis court is 74.08%, rugby field is 51.78% and rugby sevens at the USK small stadium is 71.87%. %. 67.48 percent.

The Aceh-North Sumatra PON is scheduled to be held from 8 to 20 September 2024 and will be inaugurated by the President of the Republic of Indonesia on 8 September 2024 at the Harapan Bangsa Stadium, where 33 sports will compete in 10 provinces/cities. they make up Aceh Province.

Next page

So, the construction progress of the tennis court at the SB complex is 71.87%, Gore Koni Aceh is 67.10%, tennis court is 74.08%, rugby field is 51.78% and rugby sevens at the USK small stadium is 71.87%. %. 67.48 percent.